Project Detailsx
Client:NZTA
Location:Greymouth
Year Completed:2019
Category:Pavement construction, concrete structures and traffic management
Project Overviewx
Construction of a new circular roundabout with associated works on the intersections of SH6 (High Street) and Marlborough Street in Greymouth. All earthworks including pavement surfacings, kerb construction, drainage and vehicle accesses was completed along with the concrete construction for the raised islands, footpaths and low retaining walls. Pedestrian refuge, street and crossing point lighting was installed before the surrounding area was sealed and pavement marking was completed and signage installed.
Specialist Work Required: Traffic Management- traffic flows in excess of 10000 vehicles per day.